CONSTRUCTION BEGINS ON FIFTH AVE. IMPROVEMENTS

Marble Cliff Announcements

CONSTRUCTION BEGINS ON FIFTH AVE. IMPROVEMENTS

Work is scheduled to start Wednesday April 26 on the Fifth Ave. street improvements. Done as a joint project with the City of Upper Arlington, work includes:
1. Milling and repaving West Fifth Avenue from the railroad tracks east to Andover Road.
2. Constructing a new, 8-10 foot wide, multipurpose/bike path connecting the Scioto Greenway Trail at Dublin Road/West Fifth Avenue to Arlington Avenue where the path will connect to Upper Arlington’s bike boulevard and Marble Cliff’s designated bike route.
3. Narrowing Fifth Avenue by eight feet to accommodate the new multipurpose path. Two lanes of traffic and parking on the north side of the street will be maintained with no loss of parking. All property owners will have access to their driveways during construction.
4. Installing new curbs in Marble Cliff and moving the street lights into the new tree lawn.
Completion date is set for late July.